Guazhou Xiangyang 49.5 MW wind farm in two units and put into operation successfully
Jiayuguan Gansu provincial power companies and power companies of the Group of Experts on the Jiuquan Guazhou Xiangyang Wind Farm 2 works seriously grid examination and acceptance. After Xiangyang Wind lack of a comprehensive elimination rectification.
August 19, Jiuquan Guazhou Xiangyang Wind Farm 2 33 Taiwan 1.5 MW, installed capacity of 49.5 MW of wind turbine grid running smoothly.
Jiuquan Wind Farm Phase II Guazhou Xiangyang Jiangyin vision using 33 units of energy produced 1.5 MW-class double-fed asynchronous generators, the total investment 467 million yuan. At this point, Jiuquan region and grid of the total installed wind generators capacity of 657.1 MW. This marks the first of China’s plans to build a 10 million KW-class demonstration of Jiuquan wind power base toward the goal of building a project forward in a solid step forward.